2.4. Détermination des dates au plutôt
(Tx)
Nivaux
|
Calculs de Tx
|
Tx Retenue
|
C0
|
- Ta=0
|
- Ta=0
|
C1
|
- Tb=Ta+4=0+4=4
|
- Tb=4
|
C2
|
- Tc=Tb+6=4+6=10
- Td=Tb+6=4+6=10
|
- Tc=10
|
C3
|
- Te=Tc+10=10+10=20
|
- Te=20
|
C4
|
- Tf=Te+7=20+7=27
|
- Tf=27
|
C5
|
- Tg=Tf+10=27+10=37
|
- Tg=37
|
C6
|
- Th=Tg+13=37+13
|
- Th=50
|
C7
|
- Tj=Th+28=50+28=78
- Tk=Th+28=50+28=78
|
- Tk=78
|
C8
|
- Tz=Tk+3=78+3=81
|
- Tz=81
|
Tableau 1.1.2 : Détermination des dates au
plus tôt
2.5. Détermination des dates au plus tard (Tx)
Tâches
|
Calculs de T*x
|
T*x Retenue
|
Z
|
- T*z =Tz=81
|
- T*z = 81
|
K
|
- T*k =Tz-3=81-3=78
|
- T*k = 78
|
J
|
- T*j = Tz-2=81-2=79
|
- T*j = 79
|
H
|
- T*h =Tj-28=79-28=51
|
- T*h = 51
|
I
|
- T*i =Tz-5=81-5=76
|
- T*i = 76
|
G
|
- T*g =Th-13=51-13=38
|
- T*g = 38
|
F
|
- T*f =Tg-10=38-10=28
|
- T*f =28
|
E
|
- T*e =Tf-7=28-7=21
|
- T*e =21
|
D
|
- T*d =Tz-2=81-2=79
|
- T*d =79
|
C
|
- T*c =Te-10=21-10=11
|
- T*c =11
|
B
|
- T*b =Tc-6=11-6=5
|
- T*c =5
|
A
|
- T*a =Tb-4=5-4=1
|
- T*a =1
|
Tableau 1.1.3 : Détermination des dates au
plus tard
10
2.6. Graphique potentiel
10
6
81
81
Z
27 28 F
37
10
21
20
10
7
E
38
50
13
G
I
A
5
4
B
4
0 1
6
10
C
79
5
11
76
2
13
3
28
50
51
78
79
H
J
28
78 78
K
D
C0 C1 C2 C3 C4 C5 C6 C7 C8
Figure 1.1.2 : Graphique potentiel
: Le chemin critique
: Le chemin non critique
- Le chemin critique est donné par : A, B, C, E, F, G, H,
K et la durée est de 81 jours
2.7. Calculs des marges de tâches non critiques Les
tâches non critiques sont : D, I et J
a. Marge Totale (MT)
Formule : MT=T*x -
Tx
|
MT(d)
|
=79-10=69
|
MT(i)
|
=76-10=26
|
MT(j)
|
=79-78=1
|
11
b. Marge Libre (ML)
Formule : ML=Tjx -
Tix-dx
ML(d)
|
=81-10-2=69
|
ML(i)
|
=81-50-5=26
|
ML(j)
|
=81-78-2=1
|
12