Requirement study for the business integration of the new SCADA/EMS system on the AES SONEL network in Cameroon( Télécharger le fichier original )par Mbelli Njah Fongha Polytechnic,Yaounde - Masters Engineering in Electrical Engineering(Diplome d'ingenieur de conception avec option Genie Electrique) 2009 |
3.3.1: Telecommunication systems quality assurance conformance checklist
3.3.2: Systems rollout quality assurance conformance checklist
3.3.3: Training quality assurance conformance checklist
3.3.4: Documentation quality assurance conformance checklist
CONCLUSION AND PERSPECTIVES
The complete transfer and the full ownership of this new technology by AESS which has as consequences the successful implementation of the new electricity market system in Cameroon; successful modernization/improvement of network operations management at AESS; the sustainability of the system as well as its correct implementation by the EPC contractor (Siemens), all depend on a successful business integration. Most of the aspects and requirements for a successful business integration of this new system have been cited as well as their corresponding specifications and benefits in terms of quality assurance measures for proper business integration, which was the aim of this master thesis work. The scope of this master thesis work being limited to the SCADA/EMS system on the southern grid, future work would entail a requirement study for business integration for the SCADA/EMS system on the northern grid and for the other PMS systems (SCADA/WRMS and SCADA/AMR/MMS) on the southern grid and the northern grid. Given the fact that AESS is already at the statement of work phase in the implementation of the system, the next steps of this master thesis work in the implementation of the project include Ø Business integration plan Ø Equipment installation Ø Quality data supply for the system Ø Change management plan Ø Technology transfer strategy A Perspective in research of this work is the establishment of a model for the development of specifications for the design of quality assurance softwares in installing and integrating information systems. BIBLIOGRAPHY/REFERENCES
[1] FICHTNER, AES-SONEL System Control Center and Metering System Cameroon Documents, 2006 [2] Alain Oyono, SCADA/Power Management System Project opening memo, 2007 [3] Hans Francis Simb Nag, Alain Oyono and Vincent Mainsah, TSO unbundling memo documents, 2008 [4] Hans Francis Simb Nag, Alain Oyono and Vincent Mainsah, TSO documents of the new electricity market structure in Cameroon, 2008 [5] Areva T & D, Areva T & D Bidpackage for the AES-SONEL National System Control Center and Metering System Project [6] Siemens, Siemens Bidpackage for the AES-SONEL National System Control Center and Metering System Project . [7] Larry Whitman, Business Process Re-engineering; A consolidated Methodology [8] NYISO (New York Independent System operator) Webpage, www.NYISO.com. [9] National Grid Webpage, www.nationalgrid.com/www.nationalgrid.co.uk. [10] www.wikipedia.com /requirement engineering [11] Crnkovic I, Asklund U & persson Dahlqvist, Implementing and Integrating product data [12] Dennis A, Wixon B.H and Tegarden D, system analysis and design: An object-oriented approach with UML, New York: John Willey and Sons, Inc [13] Huang G.H & Mk K.L, current practices of engineering change management in UK manufacturing industries, International Journal of operations and production management [14] United states defense acquisition press, systems engineering fundamentals, 2001 [15] Beth Gold-Bernstein, Defining business integration requirements, 09/16/2003 [16] United states general accounting office, Business process reengineering assessment guide, May 1997 [17] Thomas Davenport, Reengineering-The fad that forgot people, November 1995 [18] Furey Timothy R, a six step guide to process reengineering, 1993 [19] Harrison Brian D, Pratt Maurice D, methodology for reengineering business, 1993 [20] Mangelli Raymond L & Klein Mark M, The Reengineering handbook: A step-by-step guide to business transformation, business management association, new York [21] Mayer Richard J & Dewitte Paula S, Delivery results: evolving BPR from art to engineering [22] Underdown D.R, Transform enterprise methodology, 1997 [23] Hans Francis Simb Nag, Memo on the establishment of a subsidiary [24] William S. Davis and Dr. David C. Yen, The information system consultant's handbook: system analysis and design. [25] Dan Alexandre Seni, Vice President of SETYM technologies of Montreal, HARD AND SOFT: AN EMPIRICAL FRAMEWORK FOR THE MANAGEMENT OF TECHNOLOGY TRANSFER PROJECTS [26]Immanuel Fon Umenei, MatLab-based design of controllers for the Cameroon Power network (The Southern grid), End of course dissertation, July 2008 [27] United states defense acquisition press, systems engineering fundamentals, 2001 ANNEX
Figure 17: Generation assets and storage dams foe AES Sonel Figure 18: National System Control Center (NSCC), Douala Figure 19: North Control Center, Garoua
Figure 20: Yaoundé Control Center, Yaoundé |
|